Short answer: the gap between two pool bids is almost never the same pool for less money. It is a different pool, a smaller allowance, or work one builder left out. Put the bids side by side on the lines below and the real difference shows up fast.
First, make sure it is the same pool
Ask every builder for a scaled plan, not just a price. Then check that the plans match on the things that drive cost:
- Pool and spa size, depth and shape, including steps, benches and a sun shelf.
- Raised walls, spillways and any vanishing or overflow edge.
- Deck area in square feet, and the material.
- Water and fire features, counted one by one.
The lines to line up
| Line | What to check |
|---|---|
| Engineering | Sealed structural engineering for your lot, and a soils report where the site needs one. On the coast, whether pilings are included or excluded. |
| Permits | Every permit named: city or county, the barrier, and the state's coastal permit on oceanfront lots. Historic review in St. Augustine's districts. |
| Equipment | Brand and model of pump, filter, heater, salt system, automation and lights. "Variable speed pump" is not a model. |
| Interior finish | The product and color, not just "pebble". |
| Tile and coping | Material, size and how many linear feet. |
| Deck | Material, square feet and what goes under it. |
| Electrical and gas | Runs from the panel and meter, bonding, and the heater's gas line. |
| Drainage and restoration | Deck drains, where the water goes, and who repairs the sod and irrigation the trucks crossed. |
| Barrier | Fence, enclosure or alarms to meet Florida's pool safety law, and who permits it. |
| Demolition | If an old pool is coming out, removal and backfill priced, not assumed. |
Watch the allowances
An allowance is a placeholder amount for something not yet chosen, like tile or stone. A low allowance makes a bid look cheaper and comes back as an upcharge when you pick what you actually want. Ask each builder what their tile, coping and deck allowances buy, then compare that to the samples you like. A bid with fewer allowances and more named products is a bid you can hold someone to.
Fixed price or estimate?
Ask directly: is this the price in the contract, and what can change it? A fixed price changes only when you change the project. An estimate changes when the builder's costs do. Ask how long the price holds, how changes are priced, and whether there is a fee for changes after signing. Ours is an itemized price in your Design Book that holds for 60 days, and changes after signing that affect the structure are priced as change orders before any work happens.
How you pay
Payments should follow finished work: permits and excavation, steel and plumbing, the shell, tile and deck, then start-up. Be careful with a large deposit before any permit exists. Every payment stage should be written into the contract.
Who builds it and who answers for it
- License. Look the builder up on the Florida DBPR license search. Ours is Certified Pool Contractor CPC1461548.
- Insurance. Ask for certificates for general liability and workers' compensation.
- Who runs the job. One named project manager, and how often you will hear from them. We send an update every week.
- Warranty. What is covered on the shell, the equipment and the finish, and for how long, in writing.
- Who designed it. If a design firm drew it and a builder prices it, ask who is responsible when the two disagree.
Questions worth asking every builder
- Can I see three projects you built at this investment level, and talk to one of the owners?
- What on my lot worries you, and what did you include for it?
- What is not in this price that most people end up adding?
- How many pools do you build a year, and how many at once?
- What happens to the schedule if a permit review comes back with comments?