Most homes on Anastasia Island have a St. Augustine or St. Augustine Beach mailing address. Neither tells you who permits your pool. Here is how to work it out in five minutes, and what changes if you are on the oceanfront.
Step 1: city or county?
| If your home is | Your pool permit comes from |
|---|---|
| Inside the City of St. Augustine Beach | The city's Building and Zoning Department, 2200 A1A South |
| In Crescent Beach or Butler Beach | St. Johns County. Both are unincorporated, even though addresses read St. Augustine |
| Anywhere else on the island outside city limits | St. Johns County |
The fastest way to check is the St. Johns County Property Appraiser's record for your parcel, which shows whether it is inside a city. We pull it on the first call.
Step 2: is the state involved?
If any part of the pool, its deck or fill sits seaward of the Coastal Construction Control Line, the Florida Department of Environmental Protection has to permit it, on top of the city or county permit. Your surveyor can show the line on your survey.
When the state is involved, its general permit for a single-family pool shapes the design: the pool stays landward of the 30-year erosion projection, the bottom stays within two feet of existing grade or the pool is fully above it, the excavated sand stays on site, fill is capped at 700 cubic yards, and the permit is valid for two years with no extension.
Step 3: the dune and the wildlife
The island's dunes are sensitive. Parts of the dune system are home to the endangered Anastasia Island beach mouse and to gopher tortoises, and state rules keep construction traffic and material storage off vegetated dunes unless a permit allows it. Equipment access is planned around that from the start.
Step 4: lighting
St. Johns County's land development code regulates beachfront lighting to protect nesting sea turtles, and the nesting season runs May 1 to October 31. That affects every light you can see from the beach, not just the pool. We aim pool lights back toward the house, specify low, shielded and amber-capable fixtures, and set the automation so the season takes care of itself.
Step 5: plan the timeline
Off the oceanfront, permitting is usually 2 to 6 weeks of a 16 to 28 week project. On the oceanfront, the state review runs in rounds and each response restarts the clock, so plan for months. On our 2026 oceanfront project in Ponce Inlet it took about eleven months from signed contract to state permit. The single best thing you can do is order the survey and soils report as soon as you decide to build.